Carpenter’s Point Roadway: Stabilization

Perryville, MD – 

We performed compaction grouting for the stabilization of Greenbank Road.  Improper placement of backfill from the construction of a sanitary sewer line caused significant on-going settlement of the roadway. The sewer line trench ranged from 15 to 20 feet below the roadway surface.  Compaction grouting was determined to be the most reliable method to permanently fix the problem.

We worked with the engineer to develop an approach to satisfy the project requirements.  After soil testing and base line recording were complete, we injected grout into 800 linear feet of roadway.  Three rows of grout injection locations spaced on a 12-foot grid were created.  The placement of injection locations for the center row was staggered.  The placement of the locations created a frame around the sewer pipe allowing for the grout to support both sides of the pipe, for the length of the pipe.  The grouting was initiated from approximately 18 to 24 inches above the top of the pipe, and approximately 18 feet below the surface of the ground.

There was a total of 199 injection locations and a total volume of 249 cubic yards of grout placed into these locations.  The project was completed in 25 days using two grout crews.

Scroll to Top